1997.07.08 |
I |
A construction of total six multipurpose berths was approved under a Build-to-lease agreement, between PSA and Korean Ministry of Maritime Affairs and Fisheries |
|
|
|
1998.10.27 |
I |
Memorandum of understanding (MOU) between PSA and the Korean Ministry of Maritime Affairs and Fisheries was signed |
|
|
|
2000.12.13 |
I |
Heads of Agreement (HOA) was signed |
2000.10.24 |
I |
Agreement carry into effect in three phases (phase 1~3, 3 berths each). Alteration to build-to-lease agreement - between PSA and Incheon Ministry of Maritime Affairs and Fisheries |
|
|
|
2000.11.24 |
I |
Joint Venture Agreement (JVA) was signed |
|
|
|
2001.07.26 |
I |
Joint Venture Company was established (Incheon Container Terminal) |
2001.08.13 |
I |
Construction of phase 1 (40,000 DWT, 3 berths<300m long, 14m deep>) begun |
|
|
|
2004.05.18 |
I |
Construction of phase 1 completed |
2004.07.03 |
I |
Phase 1 facility opened for business |
|
|
|
2006.06.09 |
I |
Construction of phase 2 (40,000 DWT, 3 berths<300m long, 14m deep>) begun |
|
|
|
2008.08.15 |
I |
Phase 2 facility opened for business |
|
|
|
Next |
I |
Construction of phase 3 is arranged |